Installation notices-Clamp on pipeline ultrasonic flow meter

1. Avoid the installation of the machine in the water pump, high-power radio, frequency conversion, that is, there is strong magnetic field and vibration interference;

2. Select the pipe should be uniform and dense, easy to ultrasonic transmission of the pipe segment;

3. To have a long enough straight pipe section, the upstream straight pipe section of the installation point must be greater than 10D (note: D= diameter), and the downstream must be greater than 5D;

4. The installation point upstream distance from the pump should be 30D;

5. Fluid should be filled with pipes;

6.There should be enough space around the pipeline to facilitate the operation of on-site personnel.